Piles

Category: TRANSFER OF LOADS TO MORE COMPETENT STRATA

Description

Piles can be placed in earth and debris slopes, either at regular 2D spacing over the whole slide or portion thereof, to act as isolated dowels, or, more commonly, at close spacing along one or more specific alignments to form piled walls across the direction of movement (Ito et al., 1982; Hassiotis and Chameau, 1984; Soric and Kleiner, 1986;  Popescu, 1991; Reese et al., 1992; Polysou et al., 1998; Poulos, 1999) - Figure 1. 

Figure 1: Schematic section and layout (source: SGI-MI project files)

Typically, large diameter bored cast-in-situ piles are used, with diameter 800 to 2000 (most frequently 1200) mm and spacing 1.2 to 2 times the pile diameter. The advantages of this technique may be summarized as follows:

  • applicable in a variety of topographical conditions, subject to access constraints;

  • casings limit hole instability during construction and damage to green concrete in piles formed in moving slides;

  • conventional equipment may overcome thin layers of rock.

Where access is difficult and/or the depth of sliding is modest, micropiles (200 to 300 mm diameter) are also used, normally reinforced by steel pipes to maximize bending and shear resistance of the micropiles.

Pile heads are usually completed by a capping beam  to allow:

  • redistribution of horizontal loads between piles;

  • the installation of anchors, where required to improve the resistance of the wall;

  • the installation of sub-horizontal drains, where required to reduce the thrust on the wall.

Examples of applications are provided by Wilson (1970), Palladino and Peck (1972), Nethero (1982), Oackland and Chameau (1984), Isenhower et al. (1989), Rollins and Rollins (1992), Reese et al. (1992), Leoni and  Manassero (2003).

Figure 2: Typical layout (source: SGI-MI project files)
Figure 3: Double row of large diameter piles (source: SGI-MI project files)
Figure 4: Capping beam connecting pile and anchor heads (source: SGI-MI project files)
Figure 5: Rows of micropiles reinforced by steel pipes (source: SGI-MI project files)


Design methods

The design load on the pile wall may be determined in 2D limit equilibrium analyses by calculating the reaction on the vertical section corresponding to the piled wall which is necessary to guarantee, with the appropriate factor of safety, the stability of the portion of the slide located upslope of the wall in the absence of the downslope portion; in any case, the load on the wall cannot exceed passive soil pressure.

The contribution of the downslope portion can be considered only  if this portion remains stable with an appropriate factor of safety once the driving force from the upper portion is removed; even in this case, it may be prudent to consider this mass only as confinement for the stable soil below, since even very small deformation such as shrinkage in a dry season may be sufficient to reduce or completely remove downslope support to the wall.

The design loads and the stability of the downslope portion in seismic conditions are normally determined from pseudostatic limit equilibrium analyses, taking into account the excess pore pressures that may develop in the slope, where applicable.

Once the net actions imposed by the landslide on the pile wall are known, a suitable soil-structure interaction analysis is carried out by an appropriate method to determine both the reactions in the stable soil into which the piles are anchored and the effects of actions on the piles.

The spacing between the piles must be determined balancing:

  • economy and the need to avoid interference between adjacent piles during construction and with natural drainage;

  • ensuring that soil arching develops between adjacent piles and that the soil does not “flow” between the piles.

The check that soil arching develops between adjacent piles and that the soil does not “flow” through the piles can be done by means of  analytical (simplified) tools (see for example Ito and Matsui, 1975) or 3D numerical analysis.

Provided soil arching is guaranteed, plain strain 2D soil-structure interaction analysis is representative of actual conditions, with the effects of actions on each pile being those derived from the 2D analyses, multiplied by the pile centre to centre spacing. The same analysis may be used to determine the optimal length of the piles and the benefit of anchors.

The calculation of the pile capacity in relation to the soil/structure interaction may be carried out according to several approaches and simplified methods (De Beer, 1977; Viggiani, 1981; Hassiotis and Chameau, 1984; Cantoni et al, 1989; Pearlman and Withiam, 1992).

Finite elemnt methods may be used instead to provide a simultaneous and consistent estimate of the soil-structure interaction both with the sliding mass and with the underlying stable soil. Finite element analyses in the time domain can also be used to refine the evaluation of the performance of the structure under seismic conditions.

The mechanical charateristics of the piles must be adequate to sustain the actions and the effects of actions on the piles. The structural checks must satisfy all applicable codes and standards on the subject.



Functional suitability criteria

Type of movement

Descriptor Rating Notes
Fall 0 Best suited to slides and the slide-like portion of complex landslides. May be applicable in some cases to prevent the triggering of slides with the potential to turn to spreads or flows, but are substantially ineffective once fuidification has occurred.
Topple 0
Slide 8
Spread 4
Flow 4

Material type

Descriptor Rating Notes
Earth 8 Difficult, very expensive and typically inappropriate in rock. Tools and temporary hole support to be selected taking into account ground conditions. Special care must be excercized where the ground contains large boulders which preferably should be overcome without causing excessive vibration.
Debris 8
Rock 0

Depth of movement

Descriptor Rating Notes
Surficial (< 0.5 m) 0 Typically:
· best suited where the movement is medium deep (3 to 8 m),
· inappropriate in shallower movements because excessive,
· difficult (large diameter, multiple rows) in deep movements,
· not applicable in very deep movements.
Shallow (0.5 to 3 m) 4
Medium (3 to 8 m) 8
Deep (8 to 15 m) 4
Very deep (> 15 m) 0

Rate of movement

Descriptor Rating Notes
Moderate to fast 0 Workers’ safety and end result require construction to take place when movement is extremely slow or very slow (maximum 1.5 m/year, corresponding to approximately 5 mm/day).
Under special conditions and taking due precautions (permanent casing; drilling non-stop to avoid blokage and brocken piles, it may be carried out when movement is ”slow” (up to 1.5 m/month, corresponding to 5 cm/day) .
Slow 4
Very slow 8
Extremely slow 8

Ground water conditions

Descriptor Rating Notes
Artesian 2 High groundwater levels can be dealt with by standard pile construction procedures, bu artesian groundwater conditions pose special problems during construction, possibly making piles not feasible in extreme cases.
High 6
Low 8
Absent 8

Surface water

Descriptor Rating Notes
Rain 8 Water courses need to be temporarily diverted or reliably dry during construction.
Potential pollution of watercourses by piling operations (for example by drilling fluid and/or by grout) may impose restriction on construction procedure.
No problems once the works are completed, except possibly when piles provide an undesired ”hard bank” to watercourses.
Snowmelt 8
Localized 8
Stream 8
Torrent 2
River 2

Reliability and feasibility criteria

Criteria Rating Notes
Reliability 8 Reliable performance in well characterized landslides; in first time slides it depends on estimate of piezometric regime and apprporiate operational strength parameters of soil, which can be problematic; problems may occur during construction, for example if unforeseen boulders are encountered.
Feasibility and Manageability 10 Technique and design process are well established and widely used in suitable conditions.

Urgency and consequence suitability

Criteria Rating Notes
Timeliness of implementation 6 Requires specialist equipment and techniques; implementation may need temporary roads and working platform for safe operation.
Environmental suitability 4 will be updated
Economic suitability (cost) 4 Relatively expensive.

References

  • Anagnostopoulos C., Georgiadis K. (2004). ”Stabilization of a highway with piles in a landslide area”. In: Lacerda W.A., Ehrlich M., Fontoura S.A.B., Sayao A.S.F. (eds.) ”Landslides: Evaluation and Stabilization”,  Taylor & Francis Group.

  • Cantoni R., Collotta T., Ghionna V.N., Moretti P.C. (1989). ”A design method for reticulated micropiles structures in sliding slopes”. Ground Engineering, May.

  • Conte E., Troncone A. (2004). ”An analysis of piles used to stabilize slopes”. In: Lacerda W.A., Ehrlich M., Fontoura S.A.B., Sayao A.S.F. (eds.) ”Landslides: Evaluation and Stabilization”,  Taylor & Francis Group.

  • De Beer E.E. (1977). ”State-of-the-Art report: Piles subjected to static lateral loading”. Proc. of IX ICSMFE, Tokyo, Special Session 10, 547-553.

  • Evangelista A., Lirer S., Pellegrino A., Ramondini M., Urciuoli G. (2004). ”Interpretation of field measurements for slope stabilizing piles” In: Lacerda W.A., Ehrlich M., Fontoura S.A.B., Sayao A.S.F. (eds.) ”Landslides: Evaluation and Stabilization”,  Taylor & Francis Group.

  • Hassiotis S., Chameau J.L. (1984). ”Stabilization of slopes using piles: Final Report, Joint Highway Project, Indiana Department of Highways & U.S. Department of Transportation Federal Highway Administration & Purdue University, Purdue University, Interim Report.

  • Hassiotis S., Chameau J.L., Gunaratne M. (1984). ”Design method for stabilization of slopes with piles”. Journal of Geotechnical and Geoenvironmental Engineering, ASCE, Vol. 123, n° 4, 314-323.

  • Hong W.P., Han J.G., SongT.S., Shin D.S. (2004). ” Reinforcement effect of stabilizing piles in large-scale cut slope”. In: Lacerda W.A., Ehrlich M., Fontoura S.A.B., Sayao A.S.F. (eds.) ”Landslides: Evaluation and Stabilization”,  Taylor & Francis Group

  • Hong W.P., Han J.G. (1996). ”The behavior of stabilizing piles installed in slopes, In Landslides Glissements de terrain, Kaare Senneset editor, Balkema, Rotterdam

  • Isenhower W.M., Wright S.G., Kayyal M.K. (1989). ”Design procedures for slide suppressor walls”. In: Transportation Research Record 1242, TRB, National Research Council, Washington D.C., 15-21

  • Ito T., Matsui T. (1975). ”Method to estimate lateral force acting on stabilizing piles”. Soils and Foundations, vol.15, n° 4, 43-59.

  • Ito T., Matsui T., Hong W.P. (1982). ”Extended design method for multi-row stabilizing piles against landslide”. Soils and Foundations, vol.22, n° 1, 11-13.

  • Leoni F., Manassero V. (2003). ”Consolidamento e rinforzo dei pendii in terra”. Proceedings of the 19th Conference of Geotechnics of Turin (CGT), Turin (Italy), (in Italian).

  • Nethero M.F. (1982). ”Slide controlled by drilled pier walls”. In: Application of walls to landslide control problems, Proc. of two sessions, ASCE National Convention, Las Vegas, R.B. Reeves editor, 61-76

  • Oackland M.W. and Chameau J.L.A. (1984). ”Finite element analysis of drilled piers used for slope stabilization”. In: Laterally loaded deep foundations: analysis and performance, Special Technical Publication 835, ASTM, Philadelphia, PA, 182-193

  • Palladino D.J., Peck R.B. (1972). ”Slope failures in an overconsolidated clay, Seattle, Washington”. Geotechnique 22, 4, 563-595

  • Pearlman S., Withiam J.L. (1992). ”Slope stabilization using in situ earth reinforcements” ASCE Conference, Berkeley.

  • Polysou N.C., Coulter T.S., Sobkowicz J.C. (1998). ”Design, construction and performance of a pile wall stabilizing a landslide”. Proc. of 51th Canadian Geotechnical Conference.

  • Popescu M.E. (1991). ”Landslide control by means of a row of piles”. Slope Stability Engineering, Thomas Telford, 389-394.

  • Poulos H.G. (1999). ”Design of slope stabilizing piles”. The University of Sydney, Department of Civil Engineering – Centre of Geotechnical Research, May.

  • Reese L.C., Wang S.T., Fouse J.L. (1992). ”Use of drilled shafts in stabilizing a slope”. Proc. of a Specialty Conference on Stability and Performance of Slopes and Embankments, Berkeley, California, R.B. Seed and Boulanger R.W. editors, Geotechnical Special Publication 31, ASCE,.1318-1332.

  • Rollins K.M., Rollins R.L. (1992). ”Case histories of landslide stabilization using drilled shaft walls”. In: Transportation Research Record 1343, TRB, National Research Council, Washington D.C., 114-122 

  • Shmuelyan A. (1996). ”Piled stabilization of slopes”. In Landslides – Glissements de terrain, Kaare Senneset editor, Balkema, Rotterdam

  • Soric I., Kleiner I. (1986). ”Stabilization of a landslide with anchored bored piles”. Proc. of 8th Danube-European Conf. on SMFE, 341-348.

  • Viggiani C. (1981). ”Ultimate lateral load on piles to stabilize landslides”. Proc. of X ICSMFE, Stockholm, vol. 3, 555-560.

  • Wilson S.D. (1970). ”Observational data on ground movements related to slope instability”. 6th Terzaghi Lecture, Journal of the Soil Mechanics and Foundations Division, ASCE, 96, SM5, 1521-1544

back to top